Select your utility service providerNational Grid (Rhode Island)
Total number of electric utility accounts:25
Average annual energy use (kWh):3,500,000
Average annual energy spend ($):$600,000
If unknown, click here
If unknown, click here
Please name/describe your RFPRhode Island Remote Net Metering 2
How many kWh do you seek to procure?
How many sites will be included in this RFX?
Procurement TypeCompetitive Bid: Public
Please add all the addresses to be considered for on-site projects
Specify kWh or % of total use100%
Project Types (Check all that apply, or that you would like to consider)
“Please upload a document which specifies all the sites included in this RFX. Please include the Address, City, State Zip code and any brief description of the site.
Maximize project size and/or kWh3,500,000
Project Type
Energy, Procurement and Project Goals

Energy, Procurement and Project Goals

This information will be used as the starting point for building your custom procurement.

Contract Type(s) (Select any contract options that you would like to consider in this RFX)
Spacer
REC OwnershipUndetermined/Optional
Does a Hard copy of the pricing bid need to be submitted?Yes
Name
Other (Describe)
TitleManaging Partner
Contact NameJulian Dash
Enable public comments?Yes
EmailEmail hidden; Javascript is required.
Phone(401) 454-1570
StateRhode Island
AddressProvidence
City225 Dyer Street 2nd Floor
Overview Information

Overview Information

Please provide the requested detail on your custom RFX needs.
This information will be used to build your custom RFX, and will be available for edit and approval at any time.

Please provide a brief description of your organization

Insert a brief description of your organization.  An example could be:

[CLIENT] is  a public agency, whose mission is to [FILL IN THE BLANK].  [CLIENT] services X number of constituents, with total annual electricity use of X kWh with a cost of $X over X utility accounts.

Zip02903
Please provide a brief description of the renewable energy project you are seeking

Insert any general goals for this RFX.  An example description could be:

It is the goal of [CLIENT] to be powered 100% from new renewable energy sources, while reducing [CLIENT] utility costs.

OrganizationCopacity, LLC
Please list any specific/unique RFX GOALS. Goals include items that Client would like to have as part of RFX response, but are not absolutely required
Please provide any specific language that Client requires, or otherwise would like incorporated into the RFX. Alternatively, please upload a template RFP that your organization uses, the includes language that must be incorporated in any RFP issued by your organization.
Is there a procurement/review team in place:
Please list any specific/unique RFX REQUIREMENTS. Requirements include items that Client must have part of RFX response
Upload template
Name
Will RFP have a Pre-Bid meeting?
Is Pre-Bid meeting mandatory?
Scheduling

Scheduling

Pre-bid meeting location
RFX Issue Date03/28/2022
Pre-bid meeting date04/04/2022
Pre-bid meeting time
Virtual meeting link
Zip
City
Will RFP have a Site Visit for potential respondents?Yes
Address
Site Visit meeting time
Is Site Visit mandatory?
Address
Site Visit meeting location
Virtual meeting link
Site Visit meeting date
City
State
Zip
Scheduling

Please use the table below to establish the milestones and timeframes for this RFX. The Copacity platform automatically outlines recommended milestones and dates, based on your RFX issue date.

These categories and dates are optional and can be edited if needed, and additional milestones and dates can be added at the end of the page.

Date
Pre-bid meeting (recording posted to Copacity platform immediately following)Milestone #2
RFX issue date (Copacity platform opens RFP for registration and communication)Milestone #1
Date04/11/2022
Copacity Recommended RFX Schedule:
Date04/18/2022
Date03/31/2022
Deadline for submittal of Questions.
Site visit (if applicable)Milestone #3
Date
Posting of answers to questions to Copacity platform
RFP due (Copacity platform closes)
Respondent interviews (if applicable)
RFX End Date04/29/2022
Date
Date
Scoring

Scoring

Please use the table below to establish the evaluation and scoring categories for this RFX. The Copacity platform automatically outlines recommended categories and points, however these are optional and can be edited if needed, or used as is.

You can opt to either use/assign points to each of the evaluation and scoring categories, or simply leave them as general categories that will be considered during your review and evaluation of responses.

The suggested categories and points can be edited if needed, or used as is. Additional evaluation and scoring categories can be added at the end of the section.

Additional Client specified milestones or events
Developer experience, qualifications and financial strengthEnter Scoring Factor #1 Here
Project overall feasibility (development, interconnection, permitting and approvals risk)Enter Scoring Factor #2 Here
Score 520
Project siting and designEnter Scoring Factor #3 Here
References and reference projects (5 points)Enter Scoring Factor #5 Here
Name/Organization
Score 60
Enter Scoring Factor #10 HereEnter Scoring Factor #10 Here
Total Score
Possible Score
Score 1
Section Break
Score 1
Standard RFX Language
Total Possible Score
Standard RFX documents
Utility Bills
Photos - Utility Meter(s)
Photos - Location of where electricity comes into the building(s)
Specific Distribution: Please specify a specific list of individuals/firms to receive a copy of the RFP
Template Contract documents